Highway Cutting: 4,200 m² Welded Gabion Retaining Wall

Highway Cutting: 4,200 m² Welded Gabion Retaining Wall

The project ran against a tight road-opening deadline. Cast-in-place walls were ruled out by access and program; the designer selected welded gabion boxes for their rapid, unskilled assembly and architectural face.

We supplied 4,200 m² of PVC coated welded gabions with helical binders, stiffeners and geotextile, packed and labeled section by section along the wall alignment so each crew worked from its own bundle stack.

Erection averaged 180 m² per crew-week. The wall was filled from on-site crushed rock, cutting haulage, and the interchange opened a month inside program.